How to design a Boiler Room can make it more suitable for a factory. Let’s look at the Boiler Room Design Requirements.

There are three points.

  1. Boiler Room Location Arrangement
  2. Boiler Room, Auxiliary Room, and Living Room Layout
  3. Civil Engineering Requirements

Let’s take a closer look.

First of all. we need to choose an optimal location for the boiler room.

1 Boiler Room Location Arrangement

These are the main factors that determine the location of the boiler room.

1.1 The boiler room should be separate.

1.2 We need to keep the boiler room as far away from people and buildings as possible.

1.3 If we must build the boiler room connect with other buildings or set in buildings.

We can’t build it densely populated places, and important locations adjacent to the first floor and the next floor, as well as on both sides of the main corridor and evacuation routes.

We should build it on the ground floor or basement floor portion of the building according to the exterior of the building.

1.4 We can’t build a boiler room in a residential building.

1.5 The boiler room of the coal-fired pulverized boiler.

It should try to principle the area with high environmental requirements. Areas such as residential, commercial, scenic, etc.

1.6 The boiler room of the circulating fluidized bed boiler.

We need to build it in a suburb away from residential areas.

Once we have selected the location of the boiler room, we need to make a proper layout of the interior of the boiler room.

2 Boiler Room, Auxiliary Room, and Living Room Layout

2.1 We need to properly arrange the boiler room air intakes:

The layout of the air intake has the following requirements.

1) The access port needs to have more than two.

However, if the boiler length is less than 12 meters and the boiler room area is less than 200 square meters. The exit can have one.

2) Non-independent boiler room.

There must be an employee pathway that leads to the outdoors!

3) Multi-story boiler room.

The boiler room needs to have more than 2 entrances per floor. Each floor needs to have stairs with direct access to the ground.

2.2 Arrangement of boiler room doors.

The boiler room door leading to the outside should open to the outside. boiler room of the door of the work or life through boiler rooms should be to the boiler room open.

2.3 Boiler room height requirements.

The clear height of the boiler operating site and access road should meet the needs of the lifting equipment. Its height should be higher than 2 meters.

If the height of the boiler room is “A”. The height of equipment such as the boiler drum and economizer during cooling is “B”, then A should be 0.7 m higher than B.

3 Civil Engineering Requirements of Boiler Room Design

3.1 Boiler room fire hazard classification and fire-resistance rating shall meet the following requirements:

1) Boiler room fire rating judgment

The boiler room shall belong to the class D boiler production plant.

A single steam boiler rated evaporation to 4t /h or an individual hot water boiler rated thermal power greater than 2.8Mw.

Boiler room building fire-resistance rating of not less than the secondary fire-resistance rating;

A single steam boiler rated evaporation amount less than or equal 4t /h or an individual hot water boiler rated thermal powerless than equal 2.8Mw.

The boiler room building a fire-resistance rating of not less than level 3 fire-resistance rating.

In other buildings within the boiler room. The refractory level between the boiler should not be lower than the secondary fire-resistance rating

2) Class C production plant of  Boiler Room Design

The boiler room located between the heavy oil tank and the pump room, and the light oil tank and the pump room, are both Class C production plants.

Its construction should not be less than a secondary fire-resistance rating.

Those rooms are arranged in the auxiliary boiler room.

The firewall should be set apart from other rooms;

3) Class A production plant

The boiler room of gas-fired boiler is a Class A production plant.

Its construction should not be less than two fire-resistance ratings.

The firewall should be set up between the boiler room and boiler housing adjacent surge to separate the boiler room.

The doors should open outwards and shouldn’t direct access to the boiler room.

The ground should be a non-sparking floor.

4) Explosion-proof pressure relief arrangement of  Boiler Room Design

Boiler room walls, floors, or roofing, should have corresponding explosion-proof measures.

The area should be equivalent to the boiler room area of 10% of the area of pressure relief.

The pressure relief direction is not directed to persons gather place, rooms, and walkways, nor adjacent to relief at these places.

The area of the explosion-proof pressure relief surface of the boiler room discharge bin should also meet the requirements.

When the pressure relief area can’t meet the above requirements, can use the erection of the wall and top (ceiling) of the boiler room metal explosion by linking piece as a supplement.

Note: The pressure relief area should window, skylights, quality or less 120kg / m2 lightweight roofs and walls, and other weak areas included.

5) Firewall placement.

If it is the oil and gas boiler room, we should place firewalls directly between the room of the boiler itself and the room of the auxiliaries.

Glass viewing windows for boiler operation should also be made of explosion-proof capable glass.

In addition to this, we also need to have requirements on the boiler structure.

3.2 Requirements for boiler room foundations

When the boiler room has a multilayer arrangement, boiler foundation and ground floor seams should take measures to adapt to the Settlement.

3.3 Requirements for boiler room roofs of the boiler room design

The boiler room should be set aside by the largest equipment installation hole-transporting, install windows and doors can be combined with the hole or holes provided at the load-bearing walls.

3.4 Requirements for columns in the boiler room

Boiler room column spacing, span, and interior floor to the top of the column height meet the technical requirements under the premise should be consistent with existing national standards “harmonized standard factory buildings modulus” GB50006’s.

There are a few other caveats.

3.5 Use of vibration isolation measures

When the boiler room is equipped with heavy vibration equipment such as mills, blowers, and pumps.

3.6 Installation of protective rails

When Equipment around the hole for hoist, slagging characteristics, ash and slag pool, and high platform.

3.7  Countersink joint setting of  Boiler Room Design

Chimney and flue connections, should set settlement joint.

3.8 Ventilation and lighting requirements

Walls of Windows that open area outside the boiler room, except for pressure relief requirements, should be met, should also meet the ventilation and lighting requirements

3.9 Boiler room and other adjacent buildings, its adjacent wall should be the firewall.

Of course. Hygiene requirements are equally important!

3.10 Sanitation requirements for boiler room design

Health facilities design boiler room living room should be consistent with existing national occupational health standard “Design of Industrial Enterprises hygiene standards,” the relevant provisions of GBZ1.

3.11 Requirement of Platform and Escalators

Platform and escalators should choose not to burn antiskid material. The operating platform width is not less than 800 mm, the escalator width should not be less than 600 mm. Platform and escalator clear height should not be less than 2 m. The steel ladder often used slope should not be more than 45º.